126

Use Manufacturing Execution/Production Floor Execution without posting actual time

Production floor execution (PFE) is a great interface for operators to report progress and consumed material on operations. However, in many occasions it is not wished to capture actual time spent (actually this requirement has been a reality in basically all my projects, at least for some rou...

Read more...

9 Comments

Read more... 9 Comments

Category: Production Control (465)

STATUS DETAILS
Under Review
Ideas Administrator

Thank you for your feedback. This is a great suggestion!

Currently this is not in our roadmap; however, we are tracking it and if we get more feedback and votes, we may consider it in the future.

Sincerely,

Johan Hoffmann

PM, Microsoft

94

Request new material from production floor execution interface (WMS-enabled)

with the new functionality; (Preview) Register material consumption on the production floor execution interface (WMS-enabled) you can move, from the storage locations to the resource location, more quantity than requested in the BOM (for example a full pallet) and you can consume more quantity...

Read more...

1 Comments

Read more... 1 Comments

Category: Production Control (465)

STATUS DETAILS
Under Review
Ideas Administrator

Thank you for your feedback. This is a great suggestion! We will consider this in our roadmap.

Sincerely,

Johan Hoffmann

PM, Microsoft 

77

Gantt chart should be able to sort on start date instead of production ID

We have a lot of small production orders, scheduled on a certain resource. If you open the Gantt chart directly from the resource (or resource group), the information shown is sorted by production order number (and operation ID). A possibility should exist to sort on the scheduled Start Date in...

Read more...

5 Comments

Read more... 5 Comments

Category: Production Control (465)

STATUS DETAILS
Under Review
Ideas Administrator

Thank you for your feedback.

This is a great suggestion! We will consider this in our roadmap.

Sincerely,

Johan Hoffmann, Program Manager

Microsoft.

70

Cannot save filtered view in production floor execution interface.

After filtering the columns in the production floor execution interface and saving it as a view, the filtered value disappears upon leaving or refreshing the form.


Despite being previously identified as a By-Design issue (857459), clients who are unable to filter and sort thei...

Read more...

3 Comments

Read more... 3 Comments

Category: Production Control (465)

STATUS DETAILS
Needs Votes
Ideas Administrator

Thank you for your feedback.

Currently this is not in our roadmap; however, we are tracking it and if we get more feedback and votes, we may consider it in the future.

Sincerely,

Johan Hoffmann 

PM,

Microsoft.

40

Retrieve the "finished items in process" report as known from earlier AX versions

The report "Finished items in process" was part of AX 2012 alongside with it's companions "Materials in process", "Work in process" and "Indirect costs in process". The latest three mentioned are still present in Dynamics 365, but the "Finished items in process" report is gone. It would be ver...

Read more...

2 Comments

Read more... 2 Comments

Category: Production Control (465)

STATUS DETAILS
Under Review
Ideas Administrator

Thank you for your feedback.

This is a great suggestion! We will consider this in our roadmap.

Sincerely,

Johan Hoffmann, Program Manager

Microsoft.

26

Partial release of production order quantity

Basically D365 offers a solution for a partial release of production order quantities (Release on PO > General tab > released quantity). The field description is as follows: Use this option to release raw materials for a partial quantity of the production or batch order quantity. For example, for...

Read more...

2 Comments

Read more... 2 Comments

Category: Production Control (465)

STATUS DETAILS
Under Review
Ideas Administrator

Thank you for your feedback. We would like to get a better understanding of the business impact you are here seeing. Can you provide some elaboration?

Sincerely,


Johan Hoffmann

PM, Microsoft

22

Allow RAF even if picking list fails (backflush)

Allow RAF even if picking list fails (backflush)

Business case: Customer don't allow production output to stop due to issues with material consumption of back flushed material

Issue with current support: Report as finished fails if picking list journal (backflu...

Read more...

1 Comments

Read more... 1 Comments

Category: Production Control (465)

STATUS DETAILS
Under Review
Ideas Administrator

Thank you for your feedback. Currently this is not in our roadmap; however, we are tracking it and if we get more feedback and votes, we may consider it in the future.

 

Sincerely,

Johan Hoffmann

PM, Microsoft

10

Allow cross docking PO - Prod order and Prod order- PRod order

This idea is an enhancement for the existing cross docking framework. The scenarios described below are very common in the discrete industry, especially in the complex equipment industry. scenario 1; No advanced warehousing. A production order has been released and started but there are materi...

Read more...

2 Comments

Read more... 2 Comments

Category: Production Control (465)

STATUS DETAILS
Needs Votes
Ideas Administrator

Thank you for your feedback. Currently this is not in our roadmap; however, we are tracking it and if we get more feedback and votes, we may consider it in the future.

 

Sincerely,

Johan Hoffmann

PM, Microsoft

Thank you for your feedback. Currently this is not in our roadmap; however, we are tracking it and if we get more feedback and votes, we may consider it in the future.

 

Sincerely,

<Your Name>

PM, Microsoft

 

 

9

Formula Batch Attribute inheritance for mutiple batches consumed in Batch Order

A formula for a finished good is set to inherit the values from a raw material's consumed batch (es). If there is more than one batch consumed in a production batch, the system ignores the values of the other batches' attributes that are consumed and only transfers the values of the first batc...

Read more...

0 Comments

Read more... 0 Comments

Category: Production Control (465)

STATUS DETAILS
Needs Votes
Ideas Administrator

Thank you for your feedback.

Currently this is not in our roadmap; however, we are tracking it and if we get more feedback and votes, we may consider it in the future.

Sincerely,

Johan Hoffmann 

PM,

Microsoft.

6

Gantt chart - Resource view - it should be possible to add fundamental fields like Item number and Product name

The Gantt chart provides an option to customize the left pane view.


Users can choose to display fields such as Job Type, Resource, Operation Number, and Start/End Date Time.


Additionally, it would be very useful to include the following fields: