Delivery mode in Intercompany SO line does not update with changed delivery mode from Orig PO
When we manually change delivery mode in original PO header, delivery mode does not update in Intercompany SO line, but the delivery mode is changed in Intercompany sales order header. -
When set Freeze, the plan order should be deleted when demand forecast overdue.
When Set Freeze days 5, create a demand forecast on today, after running Master plan, there have a plan order is created after 5 days.
But on next day, run the master plan again, the demand forecast was deleted as overdue, but the plan order still existed.
From customers side, as the demand forecast was disappeared as overdue, the related plan order should be deleted automatic.
-
After enable planning optimization, when item is bundle item in sales order, reservation is Explosion, Delivery date control is ATP, can not firm the sales order
After enable planning optimization, go to all sales order, create a new sales order by Reservation = Explosion, Delivery date control = ATP, Add a bundle item in sales order line. Confirm the sales order, there have error pop-up ‘Requirement calculation of order 5551usmf This operation triggered master planning which is not supported when the Planning Optimization is enabled.’
-
Add Calculation factor per unit in Calculation details for cost and price report
As there don't have cost price like Calculation factor per unit in Calculation details page, so customer can't check the cost price directly in report. It would improve the system convenient.
-
DDMRP Average daily usage calculation base on actually usage not only base on inventory unit decimals.
Customer sales of 1 Pcs in last 10 days and as per DDMRP past method it should be 1/10=0.1 Average daily usage, but system is calculating Average daily usage as 1.
So they get 5 min and 24 max, by following formula, it's too much for the customer to purchase, so they think we may have an option to make the ADU is calculated base actual usage.
Min is calculated by following formula, so it 1(Average daily usage)*5(purchase lead time)*0.8(Lead time factor) = 4, 4(Red base) * 0.3(Variability factor) = 1.2, so the Min = 4+1.2 ≈ 5.
- Red base = ADU × Decoupled lead time × Lead time factor
- Red safety = Red base × Variability factor
- Red zone = Red base + Red safety
The Record point is Min+Yellow zone, Yellow Formula as following, so the Record point = 5 +1(Average daily usage)*5(purchase lead time) = 10
- Yellow zone = Average daily usage (ADU) × Decoupled lead time
The Max = the record point + Green zone, The green zone is calculated as the maximum result of the following three equations: so the Max = 10 + 14(Max) = 24
- Minimum order quantity 0
- ADU × Order cycle 1*14
- ADU × Decoupled lead time × Lead time factor 1*5*0.8
-
My quotations go to All quotations after refresh when enable Sales quotation details performance enhancement.
My quotations go to All quotations after refresh when enable Sales quotation details performance enhancement. Customers wait to keep on My quotations page as only need to do business on my quotations.