BUG: Solution to prevent an Imbalance of general ledger transaction through a scanning action
Below issue is dicsussed as high prio with Microsoft and it was forwarded after several discussions to the idea portal.
During production report as finished it is possibile to scan a quantiy with more then 15 digits and with some specific item cost resulting in a extensive i...
Adjust functionality gross requirement with planning optimzation
With the implementation of planning optimzation Forecastplanning & Gross requirement functionality is deprecated. On the release product page it is not possibile anymore to use the gross requirement button.
Solution implement a parameter on the masterplan that indicate that i...
Purchase lead time based on working days is only calculated based on coverage group, not on vendor calendar (difference between planning otpmization & Old masterplanning)
When using purchase lead times with checkbox 'working days' marked the Old master planning uses the vendor calendar as highest priority to use working days. With planning optimization this working day is ignored and only coverage group calendar is used.
Show forecast consumption actuals
Currently within F&O there is no insight in what is the status of the forecast consumption on a demand forecast.
This would be a big improvement for the current functionality.
Default order settings different per vendor
Currently Microsoft introduced new functionality related to multisourcing products.
When sourcing items by multiple vendors, it happens often that clients would be able to define different default order settings. Within the current solution this is not possibile.
Default order settings different per vendor / multisourcing with specific order settings per vendor
Currently Microsoft introduced new functionality related to multisourcing products.
When sourcing items by multiple vendors, it happens often that clients must be able to define different default order settings. Within the current solution this is not possibile.
Include explosion of phantom items during creating of manual created planned orders
With the current logic of planning optimization there is a gap for the firming of manual created planned (batch)orders. Those will not get exploded after firming.
As the production order is created in status sheduled you would expect planning arranged the explosion of the pha...