When assigning a work order to a crew through the shedule board, the system will create bookable resource bookings for the bookable resource of the crew as well for the underlying resources connected to that crew in case those resources are available. However if those resources are not available, these bookings are not created (logically) but the user doesn't get any warning about this. because of this, the planner doesn't know if the order is now planned correctlly or not. How can we avoid this. Related to this question: in case you move the booking of the crew, to a moment that all linked resources are available, the system doesn't create the bookings for those resources in case those were not created from the beginning. How to solve this.