When confirming dates on an intercompany sales order header to push confirmed dates on lines, the requested dates are also pushed from header to lines.
Result is that requested dates on lines are modified both on the intercompany PO and the intercompany SO.
In no case requested dates should be driven by the intercompany sales order (they are indeed greyed out on the intercompany sales order), they should be driven by the intercompany purchase order.

Suggested fix: for intercompany sales order, disable update of requested dates from header to lines.

Refer to LCS: 2109230050002449
STATUS DETAILS
Needs Votes
Ideas Administrator

Thank you very much for your input. We do not have any plans to extend this capability, we will however continue to monitor how much in demand such a capability is.

Comments

A

https://fix.lcs.dynamics.com/Issue/Details?bugId=626684&dbType=3&qc=bbbaa05efa7d073032c10ed48002244589977902b9ca7f0f8bdc4af50f98f03f

Category: Procurement and Sourcing