We would like to have the capacity constrained resources in a work center greater than 1, adjusted to the number of capacity in the work center. This is now a great loss. Many companies have a work center with similar multiple machines on which the products can be made. Still, they would like to use capacity constrained resources. This is to immediately determine a correct delivery time and lead time when the production order is created.
Example: One company has 4 similar bending machines. All machines can make the product that is offered. This means that the capacity of the work center is 4 times more than the current 1.
Comments
This almost feels like a bug, why is it possible to have a capacity constrained resource on a machinecenter, but not on a workcenter? It might have a good explanation but I can't find it. Would like to hear from the Business Central Team!
Category: Manufacturing
Business Central Team (administrator)
Thank you for this suggestion! Currently this is not on our roadmap. We are tracking this idea and if it gathers more votes and comments we will consider it in the future. Best regards, Business Central Team