When reporting progress in Production floor execution, the job card is created successfully, but the system defaults to using the resource cost rate instead of the actual worker-specific cost rate, leading to discrepancies in cost accounting.
Business scenario: multiple workers using the same resource will have the same cost rate within current design despite having different cost category set up
Expectation: system derive the actual cost from the worker, not from the resource.
STATUS DETAILS
Declined

Administrator on 3/24/2026 2:29:42 PM
Thank you for the feedback. This capability is already supported by the Production order default parameter called: Cost category. If you set it to No, then the system will use the rates defined in the pay agreement in the time and attendance module to calculate the cost.
Sincerely,
Johan Hoffmann
PM, Microsoft