Moving around in the Gantt chart works only if ALL resources involved in the route are visible in the chart. In the case of my customer this would mean we need to select 14 resources (as an example). Not to mention that the resources have already other production orders planned in the chart. This makes the whole overview completely un-readable or you have such a big screen that you can see all of it. Customer expects that the operations not shown in the chart are also re-planned. Either automatically or at least when executing a function like “Scheduled around job”.

STATUS DETAILS