Moving around in the Gantt chart works only if ALL resources involved in the route are visible in the chart. In the case of my customer this would mean we need to select 14 resources (as an example). Not to mention that the resources have already other production orders planned in the chart. This makes the whole overview completely un-readable or you have such a big screen that you can see all of it. Customer expects that the operations not shown in the chart are also re-planned. Either automatically or at least when executing a function like “Scheduled around job”.
Comments
This would make the function useful.
peter
Category: Production Control
Johan Hoffmann (administrator) on 1/8/2020 10:23:23 AM
Thank you for your feedback.
Currently this is not in our roadmap; however, we are tracking it and if we get more feedback and votes, we may consider it in the future.
Sincerely,
Johan Hoffmann
PM,
Microsoft.