16
At the moment the work center and machine center rates have the following 3 rates:
- Direct unit cost
- Indirect cost%
- Overhead cost
Please add the following rates to (or replace Direct unit cost with) the work center and machines center rates:
- Labor setup rate
- Labor run rate
- Machine setup rate
- Machine run rate
Also make sure that the prod order routings will show the required hours and cost for:
- Labor setup
- Labor run
- Machine setup
- Machine run
And if a routing setup and/or run is finished or not
- Direct unit cost
- Indirect cost%
- Overhead cost
Please add the following rates to (or replace Direct unit cost with) the work center and machines center rates:
- Labor setup rate
- Labor run rate
- Machine setup rate
- Machine run rate
Also make sure that the prod order routings will show the required hours and cost for:
- Labor setup
- Labor run
- Machine setup
- Machine run
And if a routing setup and/or run is finished or not
STATUS DETAILS
Needs Votes
Business Central Team (administrator)
Thank you for this suggestion! Currently this is not on our roadmap. We are tracking this idea and if it gathers more votes and comments we will consider it in the future. Best regards, Business Central Team