1

Since the creation of new Priority and Decoupling point coverage groups, the planning priority field is available on planned production orders. During firming process the planning priority is defaulted on production orders.


My idea is to have the option to schedule production orders considering this planning priority as a constraint. So it will become possible to schedule first production orders with the lowest priority and then sort orders by priority from lowest to highest. This could be used in combination with finite capacity.


Could you please consider to add the option "Planning priority" into the popup window when we are running the scheduling batch, whatever if we are doing operations or job scheduling? Thnak you

STATUS DETAILS
Needs Votes
Ideas Administrator

Thank you for your feedback.

Currently this is not in our roadmap; however, we are tracking it and if we get more feedback and votes, we may consider it in the future.

Sincerely,

Johan Hoffmann 

PM,

Microsoft.