3

Make it possible to adjust duration on production job based on already RAFed quantities.



For example, production order is for 500 pcs, route specified 1min/pcs.

When originally scheduled, production job was for 500 mins.

Then I posted job card for 5mins and RAF journal for 150 pcs.

Then I reschedule production order.

Current result: job duration changes from 500 to 495 mins because of 5 mins already posted.

Result after change: job duration changes from 500 to 350 because there are 350 pcs to complete at 1min/pcs.

STATUS DETAILS
Needs Votes
Ideas Administrator

Thank you for your feedback. Currently this is not in our roadmap; however, we are tracking it and if we get more feedback and votes, we may consider it in the future.

 

Sincerely,

Johan Hoffmann

PM, Microsoft

Comments

O

the workaround is to create smaller production orders if there is no setup involved but this is not a popular solution with customers who produce larger batch sizes and depending on the operator or the final machine, there is a variability in the production rate when compared to the produced quantity.

Category: Production Control