  • Activate parameter "Ensure that planned orders are not created prior to the planning run date" in Planning optimization

    We are currently using the built-in MRP but we want to switch to Planning optimization for performance reasons. Currently, via the parameter "Ensure that planned orders are not created prior to the planning run date" on the plan, we have ensured that the order date of a planned order can be in the past (parameter is not active). This allows us to immediately recognize the biggest problems and not automatically postpone all other orders to the future. Only if the supplier indicates that it is not feasible we will take action. We would like this functionality back in Planning optimization.