  • "Activity number” and “project category” fields are not filled in Projects > Work Breakdown Structure

    In the Projects > Work Breakdown Structure form, when we add new tasks, system is generating the "Activity number" but it is not displaying in the Work Breakdown Structure form.


    When we clicked "edit" or "publish" button, it is disappearing.


    The same issue is occured for the "Project Category" field. Although, we defined the Project Category, it is also disappeared as "Activity number"


    1- Those 2 fields can be used to make definitions and link to another functionality (such as, fee journal lines)

    2- It generates the "Activity number" in the related table, then why it can not be shown in the Work Breakdown Structure.

    3- When we asked Microsoft experts, they proposed to make customizations. Do we really need customizations for the already existing fields?


    Best regards,

    Turgay Kayaer

    Microsoft Dynamics 365 Finance Consultant