Resource Requirement is stored according to the 24 hours
We have created our calendar template with 8 hours duration. Project Task is working fine with 8 hours. From Project teams if we generate the requirements, the Resource Request is considering as 24 hours instead of 8 hours. The duration field on the Resource Requirement is stored in days. The fa...
STATUS DETAILS
Needs Votes