Planning Optimization does not consider Vendor Purchase Calendar closed days when calculating Delivery Date due to Lead time days


Summary:

If a Vendor typically shuts down completely for a month (ie Chinese holiday season) or typical 2-3 week MFG holiday shutdown or yearly long-term plant maintenance.  Would like to use the Vendor's Purchase Calendar in D365FO  with Working Days = Yes to account fo...