12
Currently, there are two ways to move a booking. One is from the schedule board and another is to edit the booking record. When a project record is staffed at the beginning of the project, bookings are created for potentially the next 6 months for multiple resources. If the project schedule slips one or two weeks one month into the project, all of those future bookings will need to move out to keep maintain the accuracy of the availability of the resource on the project. Could you create functionality to accomplish this? On the Schedule tab for a Project, there is a "Move Project" button which will reschedule all the tasks but it moves every task. Could it be modified to move future tasks and could it then move the bookings associated with those tasks?
STATUS DETAILS
Planned
2023 Release Wave 2
Ideas Administrator

In the Ocotber 2023 release wave, we are working on an exprience to aling assignments and booking on a project when assignments moved due to change of schedules

Comments

M

we have the same issue. There can be a dozen resources on a project for three months, 3-4 days a week. They are booked from the anticipated project start data and if the start date slips it becomes a painful task to move the bookings.

Category: Project Resource Management