If I have an approved planned order, MRP is backing off completely .
That is good for the dates and the quantities.
A big problem is that it also freezesthe BOM>
If I get a new active BOM (pretty common with manufacturing revisions), the planned order will NOT see it and when I firm the planned order, it will become a production order with the old, no longer active BOM.
This is a VERY BIG problem.
The "approved" planned prod orders should still take the active BOM, MRP should check this for every MRP run.
That is good for the dates and the quantities.
A big problem is that it also freezesthe BOM>
If I get a new active BOM (pretty common with manufacturing revisions), the planned order will NOT see it and when I firm the planned order, it will become a production order with the old, no longer active BOM.
This is a VERY BIG problem.
The "approved" planned prod orders should still take the active BOM, MRP should check this for every MRP run.