If I have an approved planned order, MRP is backing off completely .
That is good for the dates and the quantities.
A big problem is that it also freezesthe BOM>
If I get a new active BOM (pretty common with manufacturing revisions), the planned order will NOT see it and when I firm the planned order, it will become a production order with the old, no longer active BOM.
This is a VERY BIG problem.

The "approved" planned prod orders should still take the active BOM, MRP should check this for every MRP run.