If we have 2 planned orders or 2 production orders for item A (qty =1000) and item B (qty=1000).
A is a component for B.
In the Planning, MRP will set the beginning of the production of B once the production of A is totally finished.
The requirement is to overlap both productions : we would like to be able to start the production of B once 10% of A is finished.

In standard, this is possible using 2 operations within the same production order (in the same route). But this is not possible between 2 production orders.
Category: Planning
STATUS DETAILS
Needs Votes