My customer is using production orders to reserve personnel capacity to serve their customers. Their staff works mostly from 08:00 to 16:00. When scheduling production orders, sometimes first available slot is late in the afternoon. As a result, production order could be scheduled to start on one day, then pause for 16 hours when nobody is working, and then continue in the following morning.

In my case, we would need to finish everything we start at the same day without time gaps.

So basically, we would need scheduling to check if it can complete all operations within resource’s calendar opening period, and to schedule production order accordingly.

Category: Planning
STATUS DETAILS
Needs Votes

Comments

A

In healthcare it's not convenient to continue surgery in the morning.