	In DDMRP planning methodology, there is also the concept of a non-buffered part (think of make-to-order items). The same net flow equation is used and planned orders are only then generated where the net flow is negative (On-hand + on-order - qualified demand) < 0. The exception with non-buffered managed parts are that the net flow is not compared against the buffer (because there is no buffer).