Using the "Accept Delay" function in the "Product & Supply"/"Explosion" menu of the sales order lines, the system allows you to update the confirmed shipping date on the sales order line based on the MRP detected delay. However, the system doesn't update the confirmed receipt date accordingly, which remains the previous one. I think this is obviously a bug, as it creates inconsistencies in the information, but it hasn't been recognized as a "BUG," so I need some ideas to perhaps find a fix.
STATUS DETAILS
Needs Votes

Administrator on 4/22/2026 11:47:07 AM
Thank you very much for providing this Idea. You are correct, the at present this is not supported due to a design limitation. While we do not have any plans to extend our current capabilities to cover your idea, we will however continue to monitor how much in demand lifting this limitation is. Please continue to vote if this implementing this idea will be of significant positive impact to your business.
Regards,
Supply Planning Team