13
Objective : simulate changes on resources capacities, and get results through MRP calculation => capacity reservations, planned dates, calculated delays...
Proposed feature : on top of existing resources/calendars relationships (including resources groups calendar deviation), provide new tables/forms to specify master plan dedicated values.
Datamodel : it would be possible to specify calendar value for each record based on key : Resource x Date x Masterplan.
Example : on master plan MP1, apply 7h/day calendar. For the same resource, on master plan MP2, apply a different calendar like 14h/day. (for same resource and same date).
STATUS DETAILS
Needs Votes

Administrator on 10/16/2025 1:54:35 PM
Thank you very much for your input. We do not have any current plans to provide such an extended capability in Planning Optimization. We will however continue to monitor how much in demand such an extended capability is.