Objective : simulate changes on resources capacities, and get results through MRP calculation => capacity reservations, planned dates, calculated delays...
Proposed feature : on top of existing resources/calendars relationships (including resources groups calendar deviation), provide new tables/forms to specify master plan dedicated values.
Datamodel : it would be possible to specify calendar value for each record based on key : Resource x Date x Masterplan.
Example : on master plan MP1, apply 7h/day calendar. For the same resource, on master plan MP2, apply a different calendar like 14h/day. (for same resource and same date).
Comments
Most customers want to be able to simulate what would happen with regard to capacity planning if they change labor shifts.Ideally analysis of the current plan against the simulated plan would be provided too. Then AI can deliver advice to the customer on how to proceed.
Category: Planning