We need support to handle recurring tasks, as can be done in MS Project, Outlook etc. This becomes especially important when we win the work and move to resource scheduling.
E.g. I need a Project Manager to spend 1 day per week on a project that lasts 6 months.
At present the system will divide the effort by the duration and show a fraction of time every day for 6 months. This does not assist with resource scheduling because I cannot see how many actual days they are busy. It could also be specific days required. Like MS Project and MS Outlook can do at present. Thanks