440

Situation :

Planning Optimization replaces the usual Master Resource Planning.

Within this Planning Optimization, CTP capability has been added, it becomes GA in 10.0.32.

But : this CTP is not yet able to run on the fly, when user saves the sales line. It's necessary to re-run the master plan. We are then loosing reactivity.


Idea : The request is then : retrieve instant capabilities of the existing CTP with the old MRP :

  1. Be able to request manually a delivery date control, on each sales line. Get an immediate information.
  2. Have a setting to activate by default this delivery date control, when user saves the line. If a risk of late delay is detected, inform the user with the form : "Requested delivery date can not be promised..." And visibility on alternative possible delivery dates (as the existing form).
Category: Planning
STATUS DETAILS
Completed
Ideas Administrator

Thanks for your input! This will be available from 10.0.41. Please enable its feature "Near real time CTP for Planning Optimization" in feature management. 

Sincerely,

Beatriz Nebot Gracia

Product Manager, Microsoft