1

In production scheduling (and planned order grid), planners rely on the Gantt resource view to validate execution sequence before and during firming.

Currently, orders are not consistently displayed in true start-time sequence, and planned orders cannot be easily isolated from firmed orders on the same resource.

The system should:

  • Default to sorting operations/orders by scheduled start date/time (ascending) so the resource view reflects actual execution order
  • Provide a toggle to include/exclude planned orders to distinguish future supply signals from firmed production

Without this, planners must manually interpret sequencing or adjust views, which increases effort and introduces risk when firming and validating schedules.

This enhancement aligns the Gantt resource view with real-world scheduling practices and improves confidence in execution sequencing.

Category: User Experience
STATUS DETAILS
New