2

We should be able to increase job management using another kind of job progress evaluation using a Physical Percent Progress of a job, not based on the time only as it is exsiting today but on real physicial progress of a job.


Let's imagine that a job that requires to install 100 meters of cable by day. depending of any constraint, some days i can install 50 meters, or 70, so it would mean that I have done 8 hours a job, but only intalled 70 meters.


This point change the view and allow project manager to include a real job progress for more analysis and a better estimation for the remaining work and expense, in order for example, to charge customer at any moment of the job instead waiting the end.


Hicham

STATUS DETAILS
Needs Votes
Ideas Administrator

Thank you for this suggestion! Currently this is not on our roadmap. We are tracking this idea and if it gathers more votes and comments we will consider it in the future. Best regards, Business Central Team