As requested , please find the business process and business impacts below:

 

Business Process :

 

Legal Entity A

Legal entity B

Legal Entity C

Requirement Date

(Purchase order)

Order Date

(Purchase order)

Ship Date

(Sales order)

 

Ship Date

(Sales order)

 

12/9/2024

10/10/2024

12/9/2024

 

12/9/2024

 

       Purchase lead time

60

days

  

 

 

Based on the demand in Legal Entity A:

  1. Planned purchase orders are created in Legal Entity A from the master planning
  2. Planned purchase orders are firmed in Legal entity A and corresponding intercompany orders are created in Legal Entity A and Legal Entity B. Direct delivery is happening from Legal Entity C to Legal Entity A.
  3. The problem is with the highlighted dates, i.e. Ship dates of intercompany sales order in Legal Entity B and Legal Entity C.

 

Business Impacts : Users working in the processes related to Supply chain are getting impacted, because the delivery dates are resulting in incorrect demand planning for the delivery of the intercompany orders, which is resulting in non-fulfillment of customer orders in Legal Entity A. Hence, loss of revenue for the organization.

above is the email which is related to busi... above is the email which is related to business scenario and its impact due to interco MRP delivery date issue.


We are looking forward for this requirement in the upcoming Version.

Category: Planning
STATUS DETAILS
Needs Votes
Ideas Administrator

Thanks for your input! If it gets voted, we will consider revisiting this scenario.

To note is that there is no delay propagation using planning optimization and this is due to the fact that in each planning run in the companies, the whole planned orders are deleted, dates and planned orders are not kept (unless approved), and then they will not be modified either. 

Best, 

Beatriz Nebot Gracia

Senior Product Manager, Microsoft