Comments
I am working with the customer where duration of the project's are most often 15-20 years.
Split of the projects to separated records (to workaround the 10 years limitations) cause increase the project management effort and complexity in managing project tasks milestones and project tasks completion.
Will be great to receive feedback from PG about any idea when and if the 10 years duration limitation can be extended to higher year's number to fulfill the business project management expectations?
Thanks
Separating the default order settings parameters for production and transfer orders is a very legitimate use case in multi warehouse setup. As expressed in previous posts, production and transfer orders support different process areas in manufacturing operations. This functionality gap continues to be a pain point for our master planning team with no practical work around.
This has been a basic ask for the indian clients while transferring the asset from one location to another with in the entity generating the einvoice and eway bill is mandatory based on the monetary limits.Functionality is ideally present in transfer orders where only items are allowed but not fixed assets.Thid will be a great help if the same is developed.