Working with item requirements is not allowed if multiple funding sources are setup in the project contract that is attached to the project.
It would be very helpfull if a design change was made which allowed working with item requirements and/or project sales orders in conjunction with a project contract with multiple funding sources.
Comments
The update is the following: they've implemented it for T&M sales orders, but not for FF item requirements ;)
Category: Project Invoicing
Hello,
Is there any update on Item requirements supporting projects with multiple funding sources?
We have multiple customers with this requirements, all of them managing projects with multiple funding sources.
Kamaraju Vudata
Category: Project Invoicing
It should also be allowed to make an item requirement on a Grant projects, with or without multiple funding sources in the project contract.
Category: Project Invoicing
We also have a customization to allow us using item requirements while having multiple funding sources. It would be great to have it in the standard solution.
Category: Project Invoicing
Hi that really a missing feature many (new) consultants doesn't know this restriction in the design of the solution
we already do some dev to allow sales orders for project with multiple source
but I agree that should be in the standard solution
another missing feature in the concept is to allow change the funding source during a project posting by example post hour and change funding source
marc dubus
Category: Project Invoicing
I vote for this as well. When we decide to start using funding limits, almost all of our projects will have 2 funding sources which will eliminate our ability to use item requirement the way we want/need.
Category: Project Invoicing
Administrator on 6/10/2022 4:10:11 PM
Thanks for submitting this great idea. We have brought this in to be planned for and priortized accordingly.
Sincerely,
Andy Choi
Program Manager, Project management and accounting