The PSA does not calculate correctly when the task is being created with the predecessor.

For example: my calendar has 8 hours a day. If I plan this task with 4 hours on 1/1/18 and the next task I plan 4 hours more and use as the predecessor the last task created, the PSA calculates the task for 02/01/18. The correct PSA is to calculate the new task for 01/01/18 because my calendar is 8 hours a day.

In MS Project is the default behavior.